Hearing will deal with objections to Grangemouth Flood Protection Scheme
A hearing will take place at Falkirk Stadium next month looking at objections raised regarding the multi-million pound Grangemouth Flood Protection Scheme.
Falkirk Council has appointed an independent reporter – Sue Bell – to consider outstanding objections to the proposed scheme, which aims to carry out of works to reduce the risk of flooding to residential, community and business properties in the communities of Grangemouth, Wholeflats, Glensburgh, Langlees, Carron, Carronshore and Camelon.
The council states the “potential environmental impact of flood damage to businesses in the chemical sector” in the Grangemouth area “as a direct result of inadequate flood protection is an issue of national concern”.
However, there are some people who are not so happy about the scheme


The Royal Society for the Protection of Birds (RSPB) is objecting due to the impact it believes the scheme will have on the Firth of Forth Special Protection Area and the Firth of Forth Site of Special Scientific Interest.
Forth Ports is objecting to the scheme as it is currently proposed on the “basis it is inconsistent with legislative requirements and national policy and would directly impede the management, operation, development and expansion of the Port and delivery of the Forth Green Freeport (FGF)”.
Grangemouth business Jarvie Plant is objecting due to the loss of yard space the scheme would create, while another objector stated the proposal lacked detail when it came to the scope and impact of the scheme on the area.
The hearing, which will look at justification for the scheme and the outstanding objections against it, is scheduled to take place at the Stadium Way venue on Wednesday, January 28, 2026 and is expected to last two days.
Members of the public are welcome to attend to observe and can also view the hearing documents, without payment of a fee, at the same location during the hours of 10 to 4pm and online.
The hearing will be recorded and made available shortly after the hearing concludes at www.grangemouthfloodscheme.com/hearing for those unable to attend.
Following the January hearing, the reporter will report to the council, who must then make a final decision to confirm the scheme without modifications, or confirm the scheme with modifications or reject the scheme.
Notification of the final decision by the council will be then be made public.