Underground works near Longannet could cause delays for drivers
Road users travelling near Longannet are advised that traffic management will be in place from Monday, September 21.
The works will see underground electricity cables installed, and traffic on the A985 near Longannet may face delays. Temporary traffic lights will be in place for 26 weeks, 24 hours a day from Monday to Friday. A 30mph speed limit will also be in place to reduce risk to the workforce and allow work to be carried out safely.


The works, to be undertaken by Scottish Power Energy Networks, will connect a new battery energy storage site to the electricity grid at Longannet.
Carl Olivarius, senior project manager at SP Energy Networks, said: “We will monitor and review all aspects of the traffic management throughout the project to ensure it is effective and efficient, and we will work to complete the project as quickly as possible. We apologise for any inconvenience caused while these works are underway.”