Hundreds attend special Falkirk Council hearing on hyperscale AI data centre plans

Sound problems and technical glitches marred a special hearing of Falkirk Council’s planning committee to discuss an application for a hyperscale AI data centre in Larbert.

The pre-determination hearing was held in Larbert High School’s sports hall, chosen to accommodate the numbers who were expected to attend after more than 7000 people submitted formal objections to the plans.

Hundreds of people attended the pre-determination hearing on Wednesday, with 2000 people also watching the live stream.  (Pic: LDR)placeholder image
Hundreds of people attended the pre-determination hearing on Wednesday, with 2000 people also watching the live stream. (Pic: LDR)

While hundreds attended in person, the meeting has also been watched online by more than 2000 people.

Those attending on Wednesday night had bags searched when entering the school and security staff accompanying the applicants were visible throughout the meeting.

Planning committee convener, Councillor Alf Kelly, stressed that the evening was a formal meeting of the planning committee and the audience was asked not to clap or shout out.

Representatives from the applicants, Apatura, were eager to tell the committee that the development is a “huge opportunity” for Larbert and the wider Falkirk area.

But development director, Fraser Blackwood, said they recognised the concern that has been generated by the proposals and are “coordinating further information and analysis” to provide more clarity.

The microphones, which were also being used to livestream the event, struggled to cope in the large hall and the meeting had to be halted as council officers tried to sort the issues.

Once the sound improved, several members of the public made clear that they have many concerns, including the noise, heat and pollution they fear it will generate so close to a care home, hospital and thousands of houses.

Graeme Hendry, director of Glenbervie Care Home, told the hearing how the home provides highly specialised nursing care to vulnerable adults, including some who rely on tracheostomies and mechanical ventilation to stay alive.

He has “profound concerns” about the application, but said that Apatura has “at no point approached Glenbervie Care Home to discuss how this project will affect our residents”.

One of the care home’s residents, Janet Mayo, who has advanced MS, spoke movingly about how essential the peaceful atmosphere of the care home and its garden is to the residents and of her fear that this would be disrupted.

Other contributions challenged the technical aspects of the planning application, including the lack of detail regarding storage and use of 200 back-up diesel generators and how the coolant system will work.

There were also demands for more detail about how the site will be connected to the grid and to the battery storage facility in Plean, which is in the Stirling Council area.

Campaigner Michael Maciocia told the meeting that there are “major deficiencies” in the application which he believes will make it impossible to approve.

A technical problem meant that Mr Maciocia’s comments were not broadcast during the livestream but a full recording, including his remarks, will be posted to Falkirk Council’s YouTube channel.

As well as members of the public, other consultees raising questions included the NHS Public Health and the Scottish Environment Protection Agency (SEPA).

The meeting, which lasted nearly four hours, ran well over time which meant many objectors had to curtail their remarks, while Apatura representatives had only ten minutes to attempt to answer the many serious issues raised.

As the meeting began, news filtered through that the Scottish Parliament has agreed that no AI data centre planning applications will be approved until national planning guidance has been provided to all local authorities, which is expected to take a year.

Campaigners say now that they will continue to demand answers and put pressure on politicians to reject the proposal.

Apatura pledged to set up a community liaison group, which will include local businesses, and to keep residents better informed in the future.

Councillor Kelly apologised for the technical difficulties but stressed that all contributions would be considered by planning officers before the matter returns to a future meeting of the planning committee for a decision.