Work set to begin to bring canal back to life

Work to rewater the Forth & Clyde Canal between locks 3 and 16 - on a stretch known as the Falkirk Flight - is set to begin.

Scottish Canals began work to tackle deterioration to many of the lock gates at the start of 2025.

Work has extended from the Kelpies to the Forth and Clyde Canal junction with the Union Canal at the Falkirk Wheelplaceholder image
Work has extended from the Kelpies to the Forth and Clyde Canal junction with the Union Canal at the Falkirk Wheel

As well as a major gate replacement and repair programme, engineers carried out work to embankments, masonry and lock mechanisms. In addition, a lock bypass was installed at Lock 16 to improve future water management.

However, to enable the works, the Falkirk Flight between Locks 3 and 16 had to be dewatered, and water fed downstream around the drained section using pumps and siphons.

Now Scottish Canals say they are set to begin the delicate task of rewatering the 236-year-old stretch of canal.

They say rewatering the canal will require careful monitoring, including of the embankments and canal bed for any signs of leakage.

It also involves regular attention to the natural environment and water quality, working around bird-nesting periods and ensuring aquatic life can safely return to the canal.

There will also be a major clean up task as floating vegetation, refuse and debris emerging from the canal bed emerges as water levels rise.

Most of the canal will be rewatered, however Locks 4 and 13 will remain isolated using stop planks for the final gate replacements in February.

Installing stop plank grooves along the lock flight was one of the improvements made during the works, to ensure in future locks can be sealed off individually removing the need to dewater such a long stretch of canal for any future maintenance works.

Scottish Canals say the process will be “slow and gradual”, with water introduced into each section of the Falkirk Flight in small increments.

Initial work will focus on rewatering the section from Lock 16 towards Lock 13 before progress is assessed in January.

Work will then continue on the remaining sections towards Lock 3, keeping locks 4 and 13 isolated until their new gates are in place.

Efforts are already underway to clear vegetation along the canal banks to give engineers a clear view of the embankments to monitor for any water leakage.

That is expected to involve the use of a weed harvester - a kind of amphibious tractor that can operate in water to remove overgrowth, floating debris and refuse.

Final work is also being carried out to masonry and the installation of stop planks at the two remaining locks scheduled for repair.

Once ready, water will be released through the new water-control bypass at Lock 16, initially filling the canal section up to Lock 15 before progressing down the Falkirk Flight.

Once water levels are high enough, the gates and mechanisms will be tested to ensure they are fully operational before opening the stretch of the canal to navigation again.

Scottish Canals say they anticipate the Falkirk Flight will be fully rewatered by March, with sea-to-sea navigation along the canal hoped to resume on April 23 next year.