Latest delay in report to Falkirk Council on Maddiston Primary School structural issues
Councillors and parents will have to wait a few more months before learning why a relatively new school was found to have so many structural defects.
Maddiston Primary School has been closed for almost 14 months after serious issues were discovered in the building following storm damage.
When work began to repair that damage, far more serious defects in the school which had only been open since 2007 were found.
A huge operation began to relocate hundreds of pupils and dozens of staff at other schools across the district.


Initially it had been hoped the building would reopen last August but when the full extent of the damage was uncovered this was revised with the school now scheduled to reopen to all pupils in August 2027.
Last November councillors heard the repair bill would be £14 million.
The cost of demolishing the current school and rebuilding would have been around £28 million with demolition costs on top.
A report into the root cause of the problems with the building was due to be brought to councillors last December but this week Falkirk Council said it would now go to the May 21 meeting of the executive.
It is understood that the company who undertook the original construction of the school is no longer in business.
A council spokesperson said the main contractor involved in the repair project is Ogilvie Construction Ltd.
Currently, an extension to the school which is not affected has been used since last August for the school’s youngest pupils, P1-P3, with nearby Maddiston Community Centre being used for lunches and PE.
From August this year P1-4 children will be accommodated on the campus. P5 and P6 pupils will remain at Wallacestone Primary, while P7 classes, currently at Bantaskin Primary will move to Braes High School.
Timezone classes will remain at Moray Primary and Carrongrange High School next session.
In a letter to parents last month, director of education Jon Reid explained to accommodate these arrangements, and to provide additional capacity at both Maddiston and Braes, several modular units will be installed.
He said: “At Braes High School, staff are developing an exciting transition programme which will provide an enhanced curriculum offer for learners based there, with access to facilities and subjects not normally available at the primary stage.”
He added further information on curriculum arrangements and transport planning across all sites would be shared directly with families, in due course, by headteacher Claire McGlynn.
The director said the scale of the work involved on the school building was “significant” and would include replacement of the roof and external façades, structural repairs and strengthening of the building, upgrades to mechanical and electrical systems, improvements to fire safety arrangements, and the refurbishment of internal learning and social spaces.
He said that a contractor has been on site since January and by late spring, noticeable construction activity should be taking place.
Mr Reid thanked parents for their “continued patient, flexibility and support” during the work.
He added: “Our priority remains ensuring safe, high-quality learning environments for all children throughout this period and delivering a refurbished Maddiston Primary School that will serve the community well for many years to come.”